Federal Ministry for Economic Affairs and Energy in Berlin

Image source: Pixabay

Ministry building and administrative building with conference rooms

Location: Berlin

Client: Federal Office for Building and Regional Planning

Gross floor area: 32.000 m²

Total construction costs: 14,65 million €

Costs technical building services: 5,1 million €

Realisation period : 2012-2022  

Service: CG 410 - Wastewater, water and gas systems, CG 420 - Heat supply systems, CG 430 - Room air systems, CG 434 - ???, CG 440 - HV current systems, CG 450 - Telecommunications and information technology systems, CG 460 - Conveyor systems, CG 470 - Usage-specific systems, CG 480 - Building and system automation

 

HOAI service phases: SP 3 , SP 4 , SP 5 , SP 6 , SP 7 , SP 8 , SP 9

Description: Ministry building and administration building with conference rooms, archive and administration. To meet the fire protection required by building regulations for preventive and system fire protection in accordance with the new concept. The refurbishment work is being carried out during ongoing operations in a listed building.