DINZ - Diagnostic-Internistic-Neurological-Center

Image source: decon D.E.-C. GmbH

New construction and renovation of clinic complex

Location: Dresden

Client: Staatsbetrieb Sächsisches Immobilien- und Baumanagement, NL DD II & ASSMANN Beraten+Planen

Gross floor area: -

Total construction costs: 87,0 million €

Costs technical building services: 29,6 million €

Realisation period : 2006-2011  

 

HOAI service phases: SP 5 , SP 6 , SP 7 , SP 8 , SP 9

Description: The new DINZ building (building 27) extends in an east/west direction to the south of buildings 19 and 25. The total construction costs amounted to approx. € 87.0 million, of which the technical part was approx. € 29.6 million. The entire complex of the DINZ with a target number of beds of 411 places was planned barrier-free or adapted in the old building. Within the new DINZ building project, the neighboring building 19 was converted and refurbished.